AP1000核电站第一跨防水淹设计研究

Research on the Prevent Flooding Design for the First Bay in AP1000 Nuclear Power Station

  • 摘要:
        目的   为了增加CCS系统泵和电机在事故工况下的可用率,需要对布置在汽轮机厂房第一跨中的管道破裂情况进行分析。
        方法   为了方便计算,先对各种工况进行一定的假设,然后逐一工况分析,并通过管道建模、流体分析等方法进行计算。
        结果   通过计算核实,在破管最大流量的工况下,可以满足CCS泵及电机不淹没。
        结论   本计算方法正确有效,可以为后续项设计提供指导。

     

    Abstract:
        Introduction   To improve the utility of pump and motor in CCS system, it is necessary to evaluate the condition of pipes located in first bay of nuclear power station turbine plant.
        Method   For the convenience of calculatiion, different pipe conditions were evaluated with several proper assumptions. Mathematical modeling and fluid mechanic analysis were also applied in the evaluation.
        Result   Our evaluation indicates that CCS can still work safely even in the most unfavor assumption on the maximal flow of broken pipe.
        Conclusion   Our method shows correct and solid result in evalution and the method is expected to be applied in design of subsequent constructions in the future.

     

/