装配式配电站在配电网建设中的应用探讨

Discussion on the Application of Assembled Distribution Station in Distribution Network Construction

  • 摘要:
      目的  为解决当前配电网建设普遍存在的工期紧张、工程质量参差不齐且难以全面监控、容易造成环境污染等问题,对装配式配电站在配网建设的实际应用进行了探讨。
      方法  文章从设计、施工工艺、综合效益对比三个方面,对装配式配电站应用进行了全面分析。
      结果  与传统现场作业方法相比较,装配式配电站能够大幅缩减施工工期50%~60%,提升施工质量,减少资源消耗,降低对周围环境的影响。
      结论  灵活运用装配式配电站能有效解决前述问题,装配式配电站在配电网建设中具有较高的推广应用价值。

     

    Abstract: Introduction In order to solve the problems such as tight schedules, uneven construction quality, difficult construction quality monitoring, and possible environmental pollution, this paper discusses the practical application of prefabricated power distribution station in distribution network construction.
      Method  This paper analyzed the application of prefabricated power distribution station from three aspects: design,construction technology and comprehensive benefit comparison.
      Result  Compared with the traditional on-site operation method, the prefabricated distribution station can greatly reduce the construction period by about 50%~60%, improve the construction quality, reduce resource consumption and reduce the impact on the surrounding environment.
      Conclusion  Flexible use of prefabricated power distribution station can effectively solve the above problems. The prefabricated power distribution station has a high promotion and application value in distribution network construction.

     

/