多扩头挖孔桩基础在输电线路中的应用

Application of Multiple Heads Pile Foundation in Transmission Line

  • 摘要:
      目的  为了提高输电线路基础上拔承载力,节约工程造价。
      方法  提出多扩头挖孔桩基础,分析其上拔承载力计算方法,并与传统挖孔桩比较其承载力和经济性。
      结果  分析结果表明:同样承载力条件下,多扩头基础相对单扩头基础节省混凝土4%~26%,而且随着深径比增加而增大。
      结论  多扩头挖孔桩用于大型输电线路,能较大幅度提升基础上拔承载力,节省混凝土量。相同条件的多扩大头基础与单扩大头相比,上拔承载力提高了9%~34%。

     

    Abstract:
      Introduction  The paper aims to improve the uplift bearing capacity of transmission tower foundations and to save the cost of project.
      Method  In this paper, a method for calculating the uplift bearing capacity of pile foundation with multiple expanded heads was proposed, and its bearing capacity and economy were compared with the traditional pile foundation.
      Result  The results we obtained demonstrate that with the same bearing capacity, the multiple heads foundation saves 4% ~ 26% of concrete compared with the single head foundation, and increases with the increase of the ratio of depth to diameter.
      Conclusion  Our data suggest that using the multiple heads foundation in large-scale transmission lines can greatly improve the uplift bearing capacity of the foundation and save the concrete. In the same condition, the uplift capacity of multiple heads foundation improves 9%~34% comparing to the single head foundation.

     

/