      目的  文章针对全球首个500 kV海上升压站电气一次设备交接试验的电压施加方法、试验电压标准、试验套管布置方式以及试验项目顺序等多个问题进行了探讨。
      方法  基于试验条件和试验要求,对试验电压值与设备的绝缘强度进行了比较和分析。根据GIS和电缆的结构特点,使用GIS和电缆联合试验的方法对电缆施加电压。考虑海上升压站的空间环境和最大绝缘距离,选择在升压站外面布置500 kV GIS耐压试验套管。通过比较500 kV和66 kV配电设备试验项目的试验电压值大小,合理地安排试验项目顺序。
      结果  确定了主变中压绕组的耐压试验的电压施加方法、66 kV GIS试验的电压标准,以及电缆和GIS设备的试验项目顺序。在制造基地完成了变压器、电缆和GIS的交接试验。
      结论  全球首个500 kV海上升压站电气一次设备的交接试验方法能简化试验准备工作,缩短试验工期,具有一定工程应用价值,可为其他海上升压站项目提供参考。

     

    Abstract:
      Introduction  This paper explores multiple issues including the voltage application method, test voltage standard, test casing layout, and test item sequence for the handover test of the electrical primary equipment of the world's first 500 kV offshore booster station.
      Method  Based on the test conditions and requirements, a comparison and analysis of the test voltage values and the insulation strength of the equipment were conducted. According to the structural characteristics of GIS and cables, the method of jointly testing GIS and cables was used to apply voltage to the cables. Considering the spatial environment and maximum insulation distance of the offshore booster station, the 500 kV GIS withstand voltage test casing was arranged outside the booster station. By comparing the test voltage values of the test items for 500 kV and 66 kV distribution equipment, the test item sequence was arranged rationally.
      Result  The voltage application method for the withstand voltage test of the medium voltage winding of the main transformer, the voltage standard for the 66 kV GIS test, and the sequence of test items for cables and GIS equipment are determined. The handover tests of transformers, cables, and GIS are completed at the manufacturing base.
      Conclusion  The handover test method for the electrical primary equipment of the world's first 500 kV offshore booster station can be used to simplify the test preparation work and shorten the test period. The method demonstrates certain engineering application value and can be used as references for other offshore booster station projects.

     

/