海外火电厂EPC项目采购管理流程及信息化研究

于海波

于海波. 海外火电厂EPC项目采购管理流程及信息化研究[J]. 南方能源建设, 2016, 3(S1): 177-179. DOI: 10.16516/j.gedi.issn2095-8676.2016.S1.040
引用本文: 于海波. 海外火电厂EPC项目采购管理流程及信息化研究[J]. 南方能源建设, 2016, 3(S1): 177-179. DOI: 10.16516/j.gedi.issn2095-8676.2016.S1.040
YU Haibo. Regarding to Equipment and Material Management Process and Informatization Analysis in Oversea Thermal Power Plant EPC Project[J]. SOUTHERN ENERGY CONSTRUCTION, 2016, 3(S1): 177-179. DOI: 10.16516/j.gedi.issn2095-8676.2016.S1.040
Citation: YU Haibo. Regarding to Equipment and Material Management Process and Informatization Analysis in Oversea Thermal Power Plant EPC Project[J]. SOUTHERN ENERGY CONSTRUCTION, 2016, 3(S1): 177-179. DOI: 10.16516/j.gedi.issn2095-8676.2016.S1.040
于海波. 海外火电厂EPC项目采购管理流程及信息化研究[J]. 南方能源建设, 2016, 3(S1): 177-179. CSTR: 32391.14.j.gedi.issn2095-8676.2016.S1.040
引用本文: 于海波. 海外火电厂EPC项目采购管理流程及信息化研究[J]. 南方能源建设, 2016, 3(S1): 177-179. CSTR: 32391.14.j.gedi.issn2095-8676.2016.S1.040
YU Haibo. Regarding to Equipment and Material Management Process and Informatization Analysis in Oversea Thermal Power Plant EPC Project[J]. SOUTHERN ENERGY CONSTRUCTION, 2016, 3(S1): 177-179. CSTR: 32391.14.j.gedi.issn2095-8676.2016.S1.040
Citation: YU Haibo. Regarding to Equipment and Material Management Process and Informatization Analysis in Oversea Thermal Power Plant EPC Project[J]. SOUTHERN ENERGY CONSTRUCTION, 2016, 3(S1): 177-179. CSTR: 32391.14.j.gedi.issn2095-8676.2016.S1.040

海外火电厂EPC项目采购管理流程及信息化研究

详细信息
    作者简介:

    于海波(1982),男,天津蓟县人,经济师,PMP,研究生,主要从事海外大型发电项目采购物资管理研究工作(e-mail)yuhaibo@gedi.com.cn。

  • 中图分类号: TU71

Regarding to Equipment and Material Management Process and Informatization Analysis in Oversea Thermal Power Plant EPC ProjectEn

  • 摘要: 针对海外大型火力发电厂项目物资管理的问题,以管理需求为导向进行流程信息化分析。首先,从外部接口管理的分析到物资管理系统的接口需求,进而从采购内部管理流程中各环节信息化应包含的功能,最后阐述了物资编码在信息化建设的要点。
    Abstract: Regarding to the management in oversea thermal power plant EPC project, based on the requirement of management, this letter analyze the interface with other department or unit and their information input or requirement firstly; then describe the function in the process of procurement management, finally elaborate the key point for coding system in the information construction.
计量
  • 文章访问数: 
  • HTML全文浏览量: 
  • PDF下载量: 
  • 被引次数: 0
出版历程
  • 收稿日期:  2016-06-30
  • 刊出日期:  2020-07-16

目录

    YU Haibo

    1. On this Site
    2. On Google Scholar
    3. On PubMed

    /

    返回文章
    返回