浅析“十一五”及“十二五”期间抽水蓄能电站造价水平

Analysis of the Cost Level of Pumped Storage Power Station During the Eleventh Five-Year Plan and the Twelfth Five-Year Plan Period

  • 摘要: 为了适应抽水蓄能价格机制市场化对投资控制的新要求,文章运用总分和分类对比的方法,主要从概算水平、决算水平、各部分投资占比及造价水平、概决算水平对比等方面系统分析了抽水蓄能10年来的造价情况。得出抽水蓄能单位千瓦造价仍将上涨,枢纽建筑物投资的控制需要提高设计水平,而现有编规在独立费用这部分与抽蓄电站建设实际有较大出入等结论,并提出了提高造价控制水平的相关管理建议。

     

    Abstract: Adapt to the new demand for investment control during pumped storage price mechanism marketization, the method of total score and classification comparison was used in the paper, mainly from the level of budget and final accounts, each part of the investment ratio and cost level, almost closing level contrast aspects of system analyzed the cost of the pumped storage for ten years. The results show that pumped storage unit kW cost will continue to rise, the hub building investment control needs to improve the design level, the existing rules in a separate charge part has great discrepancy to the actual pump storage power station construction and so on. Some management suggestions to improve the cost control level has been put forward in the paper.

     

/

返回文章
返回