高级检索

盾构电力隧道施工监测目的和方法分析

Objective and Method Analysis of Shield Tunnel Construction Monitoring

  • 摘要:
        目的   以盾构电力隧道为例,根据其施工特点,系统分析盾构电力隧道施工监测的目的和方法。
        方法   首先,结合我国隧道施工监测布置、方法和电力隧道特点,分析指出其监测的目的和范围,并得出盾构电力隧道施工队周边建(构)筑物变形控制标准和自身结构要求控制标准;然后,分析提出盾构电力隧道施工监测的方法、应对管理措施、数据处理方法、成果提交方法和信息反馈策略。
        结果   结合某盾构电力隧道施工监测实践,分析和论证了其监测目的和方法。
        结论   研究结果对保障盾构电力隧道安全和顺利施工有重要意义,也可为其他类似工程提供参考。

     

    Abstract:
        Introduction   Taking shield power tunnel as an example, according to its construction characteristics, the purpose and method of shield power tunnel construction monitoring are systematically analyzed.
        Method   Firstly, the monitoring layout method of tunnel construction in China and the characteristics of power tunnel were combined with, the purpose and scope of monitoring were analyzed, the deformation control standards of surrounding structures and their own structure requirements were obtained; Then, the monitoring method of shield power tunnel construction, the data processing method of management measures, the result submission method and the information feedback strategy were analyzed and put forward in the paper. Combining with the monitoring practice of a shield power tunnel construction, the paper analyzes and demonstrates the monitoring purpose and method.
        Result   Combined with the construction monitoring practice of a shield tunnel, the purpose and method of the monitoring are analyzed and demonstrated.
        Conclusion   The research results provide great significance for the safety and smooth construction of shield power tunnel, and can also provide a reference for other similar projects.

     

/

返回文章
返回