火力发电厂四大管道偏差分析

The Deviation Analysis of Four Major Pipes in Thermal Power Plant

  • 摘要:
      目的  四大管道的设计、制造、安装环节均存在偏差,这些偏差在以往工程建设过程中并未造成很大影响,往往容易被忽视。随着布置的优化,当各种偏差趋势一致时有可能会影响管道的正常允许,需要对此进行研究。
      方法  通过从设计角度梳理理论计算和实际运行之间的各种常见的偏差,并且结合以往工程案例对偏差的影响过程进行了分析。
      结果  分析结果表明,当这些被忽视的常见偏差叠加后,有可能影响机组的正常运行。
      结论  理论计算和实际运行之间的偏差是无法完全避免的,需要在设计、制造、安装环节予以足够重视,及时沟通反馈,控制偏差的影响。

     

    Abstract:
      Introduction  There are deviations in the design, manufacture and installation of the four major pipes building. These deviations have not caused great influence in the previous projects construction process, and are often easily ignored. With the optimization of the layout, the normal operating of the pipeline may be affected when various deviation trends are consistent, which needs to be studied.
      Method  We analyzed various common deviations between theoretical calculation and practical operation from the point of view of design, and we analyzed the influencing process of deviations in previous project.
      Result  The analysis results show that these neglected common deviations may affect the normal operation of the unit.
      Conclusion  The deviation between theoretical calculation and practical operation cannot be completely avoided, so it is necessary to pay enough attention to design, manufacturing and installation, feedback timely , control the impact of the deviation.

     

/