高级检索

±800 kV特高压直流输电线路雷电性能及防护措施研究

Research on Lightning Performance and Protective Measures of ±800 kV UHVDC Power Transmission Line

  • 摘要:
      目的  雷击是造成±800 kV特高压直流输电线路故障的首要原因,开展输电线路防雷评估对系统的安全与稳定运行至关重要。
      方法  文章依托我国某在建±800 kV特高压直流输电线路工程,根据工程设计使用条件选用导、地线型,通过沿线各海拔、气象区分布塔型数量,确定了主力杆塔;综合沿线各塔位地面倾角、土壤电阻率、雷暴日、气象区等分布比例,评估了全线耐雷性能,并针对工程雷电特性,提出了具体的防雷优化措施,此外,还对比了电气几何模型(EGM)法中关于地形考虑的2种方法间的计算差异。
      结果  计算结果表明:工程综合雷击闪络率不满足设计参考值要求,全线以绕击防护为主,沿线雷暴日与杆塔正极侧的地形条件是防雷关键影响因素。
      结论  将全线位于C级及以上多雷区,山区正极侧地面倾角≥25°的杆塔保护角采用−15°设计后,可满足雷击闪络率不大于0.10次/(100 km·a·40 d)的防雷要求,经分析对比邻近已投运±800 kV线路的耐雷性能与实际运行数据,论述了文章计算方法及结果的合理性。

     

    Abstract:
      Introduction  Lightning strike is the primary cause of failures of ±800 kV UHVDC power transmission lines, and the lightning protection assessment of power transmission lines is critical to the safe and stable operation of the system.
      Method  Based on a ±800 kV power transmission line project under construction in China, the conductor and ground wire types were selected according to the design and use conditions of the project, and the typical towers were determined according to the altitude and meteorological area distribution along the line. After comprehensive consideration of the distribution ratio of ground inclination, soil resistivity, thunderstorm days, meteorological zone, etc. of towers along the line, the lightning protection performance of the line was evaluated and specific lightning protection measures were proposed in respect of the lighting characteristics of the project. In addition, the calculation differences between the two methods regarding terrain considerations in the EGM were compared.
      Result  The calculation results show that the comprehensive lightning flashover rate doesn’t meet the requirements of design reference value and mainly protect against shielding failure. Thunderstorm days and the terrain conditions on the positive side of tower are the key factors for lightning protection.
      Conclusion  After adopting the -15° tower protection angle, the line located in lightning areas with C level and above whose positive side ground inclination angle is ≥25° can meet the lightning protection requirements that the lightning flashover rate is not more than 0.10 fl/(100 km·a·40 d). The lightning protection performance and actual operating data of this project and adjacent ±800 kV as-built lines are compared and analyzed, which verifies the rationality of the calculation method and results in this paper.

     

/

返回文章
返回