摘要:
我国火力发电厂建设已经过了一个高峰期,厂址资源随着这次高峰期的建设越来越少,好的厂址资源已经基本被利用,现在建设或将要建设的厂址大部分都是条件较差的厂址,很多都位于边远山区,场地自然高差较大,需要大量的场平工作,具体表现在土石方工程量大、边坡及挡土墙工程量大、场地阶梯较多等。位于山区的火力发电厂,对总图进行精细化设计,可以有效地减少土石方、边坡及挡土墙工程量,减少厂区占地面积,减少拆迁工程等,带来很大的经济效益和社会效益。
关键词:
-
山区 /
-
火电厂 /
-
总平面 /
-
精细化
Abstract:
China's thermal power plant construction has been a peak, plant site resources is more and more less after the peak. Good site resources has basically been used, most of the site resources which are reserved are poor conditions, many of which are located in remote and a mountainous area. The natural elevation difference of site is larger, the specific performance is large amount of earthwork, slope and retaining wall project, more site step etc. In mountainous area of thermal power plant, fine design on the general layout, can reduce earthwork, slope and retaining wall project, reduce the plant area, and reduce the removing project, bring great economic benefit and social benefit.