Optimizing and Analysis for Main Power Building Arrangement of Power Plant with 350 MW Units
-
Abstract
The current different main building arrangements of 350 MW power plants are introduced, then the design, optimization principle of main building arrangement are analyzed and given optimizing suggestion. Modular design is used to optimize, compare and select to get the best assemble scheme for turbine hall module and boiler house module to reduce the cubage of main power building, weigh of the four main steam pipes, construction period and investment. The research shows: there has obvious advantage in building cubage and investment by combining the side bunker bay arrangement scheme for main building arrangements of 350 MW power plants. Finally, the Huaneng Jingmen (2×350 MW) cogeneration project is taken as an example which adopts the side bunker bay arrangement scheme.
-
-