Abstract
Auxiliary power consumption is related to the unit net output and the unit net efficiency, which is an important technical and economical index of fossil fuel power plants. Especially for oversea turnkey project, auxiliary power consumption is an key performance index to be judged during the bidding stage and tested during the acceptance certificate stage. International common practice is used to illustrate the meaning and the common penalty about the auxiliary power consumption. Applicable calculation method of the auxiliary power consumption is given and also the measurement during the bidding stage. The conclusion of this paper will give an guidance for more and more Chinese enterprises which go abroad.
-
-