Bingcai LIU, Xiaoqiang ZHAN, Xuming DAI, Xiaopan ZHAO, Hao HUANG. Risk Assessment of 500 kV Peng-Shen Transmission Line Tower Slope Operation[J]. SOUTHERN ENERGY CONSTRUCTION, 2019, 6(S1): 128-134. DOI: 10.16516/j.gedi.issn2095-8676.2019.S1.025
Citation: Bingcai LIU, Xiaoqiang ZHAN, Xuming DAI, Xiaopan ZHAO, Hao HUANG. Risk Assessment of 500 kV Peng-Shen Transmission Line Tower Slope Operation[J]. SOUTHERN ENERGY CONSTRUCTION, 2019, 6(S1): 128-134. DOI: 10.16516/j.gedi.issn2095-8676.2019.S1.025

Risk Assessment of 500 kV Peng-Shen Transmission Line Tower Slope Operation

More Information
  • Received Date: December 04, 2018
  • Revised Date: May 13, 2019
  •     [Introduction]   In order to ensure the safe and stable operation of overhead transmission lines, improve the stability and safety of transmission line slope, strengthen the awareness of operation and maintenance personnel of transmission line slope in mountainous areas, and improve the management ability of slope risk.
        [Method]   Taking the 34-grade tower slope of Shenzhen 500 kV Pengshen A-B Line as the evaluation object, combining with the engineering geological research methods and the accumulation of practical experience, a set of risk assessment index system conforming to the characteristics of the transmission line slope is constructed, and the risk grade of the slope is determined; and the corresponding risk control countermeasures and risk grading management measures are formulated. Emergency measures and procedures for dealing with unexpected accidents are proposed.
        [Result]   The results of slope risk assessment corroborate the actual situation of the slope. It can classify the risk grade of the slope simply, efficiently and reasonably. The corresponding risk control countermeasures and grading management measures can effectively reduce the risk of the slope.
        [Conclusion]   The proposed risk assessment methods and risk management ideas basically meet the management needs of transmission line slope, and have great practical value for improving the risk response ability of the operation and maintenance management department of transmission line slope and reducing the risk of transmission line slope.
  • [1]
    何海鹰,胡甜,赵健. 基于AHP的岩质高边坡风险评估指标体系 [J]. 中南大学学报(自然科学版),2012,43(7):2861-2868.

    HE H Y, HU T, ZHAO J. Risk assessment indexes system of high rock slope based on AHP [J]. Journal of Central South University(Science and Technology),2012,43(7):2861-2868.
    [2]
    王浩,林一夫,吴栋梁,等. 复杂路堑高边坡病害治理效果模糊层次评价 [J]. 工程地质学报,2014,22(5):936-943.

    WANG H, LIN Y F, WU D L,et al. Fuzzy hierarchy analysis for treatment effect of complex cutting high slope disease [J]. Journal of Engineering Geology,2014,22(5):936-943.
    [3]
    吴忠广,王海燕,陶连金,等. 高速公路高边坡施工安全总体风险评估方法 [J]. 中国安全科学学报,2014,24(12):124-129.

    WU Z G, WANG H Y, TAO L J,et al. Method for general risk assessment of expressway high slope in construction safety [J]. China Safety Science Journal,2014,24(12):124-129.
    [4]
    叶咸,陈华斌,吴铸,等. 山区高速公路路堑高边坡工程施工安全总体风险评估技术探讨 [J]. 公路,2018,63(3):42-47.

    YE X, CHEN H B, WU Z,et al. Study of mountain highway cut slope engineering construction safety overall risk assessment techniques [J]. Highway,2018,63(3):42-47.
    [5]
    曾铁权,高立虎. 公路路堑高边坡施工风险总体评估标准研究 [J]. 中国标准化,2017(24):123-124.

    ZENG T Q, GAO L H. Study on overall assessment standard of highway cutting high slope construction risk [J]. China Standardization,2017(24):123-124.
    [6]
    孟续峰. 山区公路高陡边坡工程施工安全风险评估分析 [J]. 公路交通科技(应用技术版),2016,12(6):125-126.

    MENG X F. Construction safety risk assessment of high steep slope engineering in mountainous area [J]. Journal of Highway and Transportation Research and Development(Applied Technology Version),2016,12(6):125-126.
    [7]
    张建伟,廖小平,魏土荣. 高速公路运营期高边坡安全风险评估体系研究 [J]. 路基工程,2015,6(44):193-203.

    ZHANG J W, LIAO X P, WEI T R. Study on safety risk assessment system for high slope of highway in operation [J]. Subgrade Engineering,2015,6(44):193-203.
    [8]
    吴忠广,申瑞君,万福茂,等. 岩质高边坡运营安全风险源辨识方法 [J]. 公路交通科技,2018,35(3):8-15+27.

    WU Z G, SHEN R J, WAN F M,et al. A method for identifying operation safety risk source of rocky high slope [J]. Journal of Highway and Transportation Research and Development,2018,35(3):8-15+27.
  • Related Articles

    [1]GUAN Yanyan. Exploration on the Offshore Wind Power General Contracting Project Risk Management Model Based on WBS[J]. SOUTHERN ENERGY CONSTRUCTION, 2023, 10(S1): 51-57. DOI: 10.16516/j.gedi.issn2095-8676.2023.S1.008
    [2]Shuai TIAN. Construction of the Whole Cycle Risk Management System of New Energy Venture Capital[J]. SOUTHERN ENERGY CONSTRUCTION, 2022, 9(1): 40-46. DOI: 10.16516/j.gedi.issn2095-8676.2022.01.006
    [3]Yanyan GUAN, Jiacai ZHUANG. Research on Schedule Management Method of Offshore Wind Power Based on Risk Management[J]. SOUTHERN ENERGY CONSTRUCTION, 2022, 9(1): 34-39. DOI: 10.16516/j.gedi.issn2095-8676.2022.01.005
    [4]Chujun LUO, Jian LI, Qinghua WU, Shengfeng ZHANG. Risk Assessment Method for Anchoring Accident of High Voltage Submarine Cable[J]. SOUTHERN ENERGY CONSTRUCTION, 2021, 8(1): 67-73. DOI: 10.16516/j.gedi.issn2095-8676.2021.01.010
    [5]Bingqian WANG, Jianmin DONG, Qianfeng GUAN, Qian HAN. Research on Risk Assessment System of Pumped Storage Power Station Using Grey Relational TOPSIS Method[J]. SOUTHERN ENERGY CONSTRUCTION, 2020, 7(S2): 56-61. DOI: 10.16516/j.gedi.issn2095-8676.2020.S2.009
    [6]Yanjie WANG, Guozhi XU. Line Loss Management Evaluation System and Verification Based on IAHP Method[J]. SOUTHERN ENERGY CONSTRUCTION, 2020, 7(S2): 25-32. DOI: 10.16516/j.gedi.issn2095-8676.2020.S2.004
    [7]HUANG Xiaoting, ZHANG Tingying, XU Zhe. Analysis on Characteristics of Singapore′s Power Market Settlement and Risk Management[J]. SOUTHERN ENERGY CONSTRUCTION, 2019, 6(4): 29-34. DOI: 10.16516/j.gedi.issn2095-8676.2019.04.004
    [8]ZHANG Li, HUANG Wenhe. Discussion on Risk Management of Offshore Wind Tower Engineering Under EPC Mode[J]. SOUTHERN ENERGY CONSTRUCTION, 2017, 4(S1): 168-173. DOI: 10.16516/j.gedi.issn2095-8676.2017.S1.032
    [9]YUAN Guokai, ZHU Guangtao, HUANG Zhijun. Construction and Installation Risk Management of Offshore Wind Farm[J]. SOUTHERN ENERGY CONSTRUCTION, 2016, 3(S1): 190-193. DOI: 10.16516/j.gedi.issn2095-8676.2016.S1.043
    [10]Ji QUAN, Jianmei HUANG, Shuibo ZHANG. System Analysis and Design for the Risk Database and Assessment and Management System of the International General Contracting Project[J]. SOUTHERN ENERGY CONSTRUCTION, 2015, 2(4): 163-169,101. DOI: 10.16516/j.gedi.issn2095-8676.2015.04.031

Catalog

    Hao HUANG

    1. On this Site
    2. On Google Scholar
    3. On PubMed

    Article Metrics

    Article views (564) PDF downloads (15) Cited by()

    /

    DownLoad:  Full-Size Img  PowerPoint
    Return
    Return