Research on Design-Led EPC Project Management of Offshore Wind Power Project

More Information
  • Received Date: March 01, 2022
  • Revised Date: March 17, 2022
  •   Introduction   In order to cope with the huge challenges of the development of offshore wind power industry in the grid parity stage and promote the sustainable and healthy development of the offshore wind power industry,
      Method   based on experience from some design-led EPC projects in China, the application of EPC mode in power engineering was analyzed, the current unique challenges and countermeasures of offshore wind power project EPC management were put forward, and the main advantages of design-led offshore wind power project in the grid parity stage were summarized from the macro level.
      Result   The research shows that the EPC mode is of great help to the cost reduction and efficiency increase of offshore wind power, especially the design-led EPC mode, which effectively mobilizes the forces of all links in the industry chain to reduce costs and increase efficiency.
      Conclusion   The research results provide a useful reference for promoting the sustainable development of offshore wind power in the grid parity stage, and will effectively promote the high-quality development of deep sea offshore wind farms in the grid parity stage.
  • YUAN Guokai,LI Yaoneng,LU Qinxian,et al.Research on Design-Led EPC Project Management of Offshore Wind Power Project[J].Southern Energy Construction,2022,09(01):1-8.

  • [1]
    蔡绍宽. 平价上网助力海上风电行业发展 ——未来五年海上风电从业同仁的使命 [J]. 南方能源建设, 2019, 6(2): 7-15. DOI: 10.16516/j.gedi.issn2095-8676.2019.02.002.

    CAIS K. Grid parity speeds up the development of offshore wind power industry——The practitioner mission of offshore wind power in the next five years [J]. Southern Energy Construction, 2019, 6(2): 7-15. DOI: 10.16516/j.gedi.issn2095-8676.2019.02.002.
    [2]
    蔡绍宽. 双碳目标的挑战与电力结构调整趋势展望 [J]. 南方能源建设 , 2021, 8(3): 8-17. DOI: 10.16516/j.gedi.issn2095-8676.2021.03.002.

    CAIS K. Challenges and prospects for the trends of power structure adjustment under the goal of carbonpeak and neutrality [J]. Southern Energy Construction, 2021, 8(3): 8-17. DOI: 10.16516/j.gedi.issn2095-8676.2021.03.002.
    [3]
    中华人民共和国住房和城乡建设部. 建设项目工程总承包管理规范: GB/T 50358—2017 [S]. 北京: 中国建筑工业出版社, 2017.

    Ministry of Housing and Urban-Rural Development of the People's Republic of China. Code for management of engineering procurement construction(EPC) Projects: GB/T 50358—2017 [S]. Beijing: China Building Industry Press, 2017.
    [4]
    王伍仁. EPC工程总承包管理模式探索及展望 [J]. 中国勘察设计, 2020(10): 40-49. DOI: 10.3969/j.issn.1006-9607.2020.10.013.

    WANGW R. Exploration and prospect of EPC general contract management mode [J]. China Exploration & Design. 2020(10): 40-49. DOI: 10.3969/j.issn.1006-9607.2020.10.013.
    [5]
    宋敏, 崔雯迪, 陈道明. 电力工程EPC总承包管理模式探究 [J]. 工程经济, 2015(8): 74-78. DOI: 10.3969/j.issn.1672-2442.2015.08.014.

    SONGM, CUIW D, CHEND M.Research on EPC general contract management mode in electrical power engineering [J]. Engineering Economy, 2015(8): 74-78. DOI: 10.3969/j.issn.1672-2442.2015.08.014.
    [6]
    贾明科, 李平平, 陈和善. EPC 总承包管理模式在风电项目中的应用 [J]. 西北水电, 2015(4): 102-104. DOI: 10.3969/j.issn.1006-2610.2015.04.026.

    JIAM K, LIP P, CHENH S. Application of EPC contracting management mode in wind power projects [J]. Northwest Water Power, 2015(4): 102-104. DOI: 10.3969/j.issn.1006-2610.2015.04.026.
    [7]
    王燕. 浅论输变电工程总承包模式 [J]. 南方能源建设, 2015, 2(增刊1): 226-229. DOI: 10.16516/j.gedi.issn2095-8676.2015.S1.050.

    WANGY. Discussion of transmission and substation EPC mode [J]. Southern Energy Construction, 2015, 2(Supp.1): 226-229. DOI: 10.16516/j.gedi.issn2095-8676.2015.S1.050.
    [8]
    刘建强. 浅谈设计类工程公司项目管理体系的构建与完善 [J]. 南方能源建设, 2017, 4(增刊1): 174-178. DOI: 10.16516/j.gedi.issn2095-8676.2017.S1.033.

    LIUJ Q. Discussion on project management construction and improvement of design class engineering company [J]. Southern Energy Construction, 2017, 4(Supp.1): 174-178. DOI: 10.16516/j.gedi.issn2095-8676.2017.S1.033.
    [9]
    张羽, 胡亮. 关于总承包业务设计优化、采购成本控制的思考 [J]. 南方能源建设, 2016, 3(增刊1): 165-167. DOI: 10.16516/j.gedi.issn2095-8676.2016.S1.037.

    ZHANGY, HUL. Design optimization and procurement cost control of EPC project [J]. Southern Energy Construction, 2016, 3(Supp.1): 165-167. DOI: 10.16516/j.gedi.issn2095-8676.2016.S1.037.
    [10]
    林幼晖. 浅谈设计院向国际工程公司转型应注意的问题 [J]. 南方能源建设, 2016, 3(1): 33-35. DOI: 10.16516/j.gedi.issn2095-8676.2016.01.007.

    LINY H. Discussion on the enterprise transformation from design institute to international engineering company [J]. Southern Energy Construction, 2016, 3(1): 33-35. DOI: 10.16516/j.gedi.issn2095-8676.2016.01.007.
    [11]
    刘晋超. 海上风电施工窗口期对施工的重要性 [J]. 南方能源建设, 2019, 6(2): 16-18. DOI: 10.16516/j.gedi.issn2095-8676.2019.02.003.

    LIUJ C. Importance of window phase for offshore wind power construction [J]. Southern Energy Construction, 2019, 6(2): 16-18. DOI: 10.16516/j.gedi.issn2095-8676.2019.02.003.
    [12]
    刘庆辉, 陆海强. 浅析海上风电施工安全管控 [J]. 南方能源建设, 2020, 7(1): 128-132. DOI: 10.16516/j.gedi.issn2095-8676.2020.01.021.

    LIUQ H, LUH Q. Brief analysis on safety management and control of offshore wind farm construction [J]. Southern Energy Construction, 2020, 7(1): 128-132. DOI: 10.16516/j.gedi.issn2095-8676.2020.01.021.
    [13]
    杨源, 阳熹, 汪少勇, 等. 海上风电场智能船舶调度及人员管理系统[J]. 南方能源建设, 2020, 7(1): 47-52. DOI: 10.16516/j.gedi.issn2095-8676.2020.01.007.

    YANGY, YANGX, WANGS Y, et al. Scheme design of intelligent vessel dispatching and personnel management system for offshore wind farm [J]. Southern Energy Construction, 2020, 7(1): 47-52. DOI: 10.16516/j.gedi.issn2095-8676.2020.01.007.
    [14]
    元国凯, 朱光涛, 黄智军. 海上风电场施工安装风险管理研究 [J]. 南方能源建设, 2016, 3(增刊1): 190-193. DOI: 10.16516/j.gedi.issn2095-8676.2016.S1.043.

    YUANG K, ZHUG T, HUAGNZ J. Construction and installation risk management of offshore wind farm [J]. Southern Energy Construction, 2016, 3(Supp.1): 190-193. DOI: 10.16516/j.gedi.issn2095-8676.2016.S1.043.
    [15]
    POULSENT, LEMAR. Is the supply chain ready for the green transformation? The case of offshore wind logistics [J]. Renewable and Sustainable Energy Reviews, 2017(73), 758-771. DOI: 10.1016/j.rser.2017.01.181.
    [16]
    广东省人民政府办公厅. 促进海上风电有序开发和相关产业可持续发展的实施方案 [EB/OL]. (2021-06-01) [2022-03-18]. https://www.gd.gov.cn/zwgk/wjk/qbwj/yfb/content/post_3316639.html.

    General Office of People's Government of Guangdong Province. Implementation plan for promoting orderly development of offshore wind power and sustainable development of related industries [EB/OL]. (2021-06-01) [2022-03-18]. https://www.gd.gov.cn/zwgk/wjk/qbwj/yfb/content/post_3316639.html.
  • Related Articles

    [1]HUANG Bin, WANG Donghui, YAO Yu. Brief Discussion on Schedule Management Planning of Guangdong Offshore Wind Power Project[J]. SOUTHERN ENERGY CONSTRUCTION, 2023, 10(S1): 38-46. DOI: 10.16516/j.gedi.issn2095-8676.2023.S1.006
    [2]MEI Shengqiang, ZHU Minhua. Research on Management of General Contracting for Electric Engineering Project Based on Digital Technology—Taking a Gas Turbine Project in South China as an Example[J]. SOUTHERN ENERGY CONSTRUCTION, 2022, 9(S2): 123-130. DOI: 10.16516/j.gedi.issn2095-8676.2022.S2.020
    [3]Yanyan GUAN, Jiacai ZHUANG. Research on Schedule Management Method of Offshore Wind Power Based on Risk Management[J]. SOUTHERN ENERGY CONSTRUCTION, 2022, 9(1): 34-39. DOI: 10.16516/j.gedi.issn2095-8676.2022.01.005
    [4]Qibing ZHENG. Application of Energy Management Contract in the Transformation of Urban LED Streetlight from Energy Service Company Perspective[J]. SOUTHERN ENERGY CONSTRUCTION, 2019, 6(S1): 6-9. DOI: 10.16516/j.gedi.issn2095-8676.2019.S1.002
    [5]YUAN Liya. Research on Procurement Schedule Management of Large-scale Power Plant EPC Project[J]. SOUTHERN ENERGY CONSTRUCTION, 2018, 5(S1): 237-241. DOI: 10.16516/j.gedi.issn2095-8676.2018.S1.043
    [6]LIU Jianqiang. Discussion on Project Management Construction and Improvement of Design Class Engineering Company[J]. SOUTHERN ENERGY CONSTRUCTION, 2017, 4(S1): 174-178. DOI: 10.16516/j.gedi.issn2095-8676.2017.S1.033
    [7]HE Runcai, TU Guofu. Procurement Cost Control in EPC General Contract Project[J]. SOUTHERN ENERGY CONSTRUCTION, 2016, 3(S1): 173-176. DOI: 10.16516/j.gedi.issn2095-8676.2016.S1.039
    [8]Jin QIN. Discussion on Engineering Optimization Management of EPC Project[J]. SOUTHERN ENERGY CONSTRUCTION, 2016, 3(1): 76-79. DOI: 10.16516/j.gedi.issn2095-8676.2016.01.016
    [9]Chuangang GUO. Study on Construction Management of Overseas Thermal Power EPC Project[J]. SOUTHERN ENERGY CONSTRUCTION, 2016, 3(1): 54-57. DOI: 10.16516/j.gedi.issn2095-8676.2016.01.012
    [10]Hao LU. Optimization of Engineering Management in the Oversea EPC Power Plant Project of Design Institute[J]. SOUTHERN ENERGY CONSTRUCTION, 2016, 3(1): 41-45. DOI: 10.16516/j.gedi.issn2095-8676.2016.01.009
  • Cited by

    Periodical cited type(8)

    1. 王震,李楠,潘继平. 油气与新能源融合发展的模式与路径. 天然气与石油. 2024(01): 1-7 .
    2. 马宇轩,闵烨,闫中杰,张坤鹏. 基于离散数值分析技术的海上风电机组安装施工规划模拟研究. 太阳能学报. 2024(06): 673-679 .
    3. 王栋杰,江越琪. 天然气发电总承包项目成本测算方法优化. 电力勘测设计. 2024(09): 28-32+58 .
    4. 罗晓健,屈衡,邓校国. 海上风电机组选型方案研究. 机电信息. 2023(03): 26-29+35 .
    5. 陈晓辉,刘聪,闫俊北. 风电工程项目建设及运营管理分析. 中国高新科技. 2023(02): 20-22 .
    6. 孙颖,李楠,和旭,何曦,张岑. 中国海上风电产业布局研究. 油气与新能源. 2023(03): 17-23 .
    7. 张铭,张宇,严祺慧,施俊佼,张波,刘鑫. 海上风电作业窗口期管理研究与系统开发. 风机技术. 2023(04): 85-89 .
    8. 张京伟,李献军,贾震江,王丽艳,周华. 海上风电总承包项目设备交付精细化管理研究. 电力勘测设计. 2022(09): 1-6+82 .

    Other cited types(5)

Catalog

    Yudong LI

    1. On this Site
    2. On Google Scholar
    3. On PubMed

    Article Metrics

    Article views (1289) PDF downloads (253) Cited by(13)

    /

    DownLoad:  Full-Size Img  PowerPoint
    Return
    Return