Abstract
The first phase of a nuclear power plant APC shell structure is made of reinforced concrete pouring, it can resist the impact of the plane, and protects the security of nuclear power plant factory. APC shell structure span is large, and having greater thickness of the wall with no horizontal and vertical support, thus the pouring of concrete quality requirement is strict. According to the APC shell structure quality requirements, the cantilever jumping formwork for concrete pouring construction is used and a construction technology of cantilever climbing formwork system is developed. By using this technique, it can ensure the pouring concrete quality and the surface flatness of the concrete wall of APC shell, and speeds up the construction progress of the wall and save a lot of manpower and resources at the same time. It has good economic and social benefits.
-
References
[1]
|
黄涛,李忠诚. 基于ANSYS/LS-DYNA的抗飞机撞击结构非线性动力分析 [J]. 核科学与工程,2015,35(4):743-748.
HUANG T, LI Z C. Nonlinear dynamic analysis of air plane crash shell based on ansys/ls-dyna [J]. Nuclear Science and Engineering, 2015,35(4):743-748. |
[2]
|
胡正春,梁峻峰,万志军,等. 台山核电厂核岛厂房土建安全设计技术 [J]. 核动力工程,2015,36(Supp.1):1-4.
HU Z C, LIANG J F, WAN Z J, et al. Safety design technology for civil engineering of nuclear island building in taishan nuclear power plant [J]. Nuclear Power Engineering, 2015,36(Supp.1):1-4. |
[3]
|
李骏,刘军,李政. 几种模板体系在EPR核电站中的应用 [J]. 施工技术,2012,41(6):70-73.
LI J, LIU J, LI Z. Application of several kinds of formwork in epr nuclear power plants [J]. Construction Technology, 2012,41(6):70-73. |
[4]
|
陈敦,田杰,田大业. 新型柱板式高墩施工关键技术 [J]. 施工技术,2015,44(4):79-84.
CHEN D, TIAN J,TIAN D Y. Key construction technology of the new column-slab high pier [J]. Construction Technology, 2015,44(4):79-84. |
[5]
|
郑群,乔传颉,于戈,等. 望京SOHO中心多体系核心筒爬模施工技术 [J]. 施工技术,2015,44(19):34-38.
ZHENG Q, QIAO C H,YU G, et al. Construction technology of core tube climbing formwork in wangjing soho center [J]. Construction Technology, 2015,44(19):34-38. |
[6]
|
牛潮,杨易琳. 台山核电水库大坝工程悬臂挂架模板施工技术 [J].施工技术,2014,43(16):70-73.
NIU C, YANG Y L. Construction technology of cantilever pylon formwork for the reservoir dam engineering of taishan nuclear power station [J]. Construction Technology, 2014,43(16):70-73. |
-
-