Zhengyu HUANG, Hanjie HU. Research on the Construction Cost Lean Management in the Preliminary Stage of Zhangzhou Nuclear Power Project[J]. SOUTHERN ENERGY CONSTRUCTION, 2018, 5(4): 135-140. doi: 10.16516/j.gedi.issn2095-8676.2018.04.021
Citation:
|
Zhengyu HUANG, Hanjie HU. Research on the Construction Cost Lean Management in the Preliminary Stage of Zhangzhou Nuclear Power Project[J]. SOUTHERN ENERGY CONSTRUCTION, 2018, 5(4): 135-140. doi: 10.16516/j.gedi.issn2095-8676.2018.04.021
|
Research on the Construction Cost Lean Management in the Preliminary Stage of Zhangzhou Nuclear Power Project
- 1.
CNNP Guodian Zhangzhou Energy Co., Ltd., Zhangzhou, 363300, China
- Received Date: 2018-02-25
- Rev Recd Date:
2018-06-10
- Publish Date:
2018-12-25
-
Abstract
[Introduction] Under the current practice of benchmarking on-grid electricity price for newly-built new nuclear power units, in order to effectively address the problems of excessively high construction cost of domestic nuclear power projects and insufficient attention to the economy of nuclear power, combining the reality of general uncompetitive domestic nuclear power on-grid electricity price in the electricity market, in order to reduce the construction cost of the Zhangzhou nuclear power project and further increase the competitiveness of the on-grid electricity price for Zhangzhou nuclear power project. [Methods] The comprehensive analysis of the construction cost for domestic nuclear power projects was made, the construction cost lean management in the preliminary stage of Zhangzhou nuclear power project was put forward. Combining the actual situation of Zhangzhou nuclear power project, the analysis of specific methods and measures for implementing cost lean management was made, in the stages of the preliminary preparation, investment decision-making, management mode selection and so on. Firstly, the land and sea acquisition mode in the preliminary stage and the innovative practice of "two-phase" procurement mode. Secondly, the optimization of current nuclear power project construction management mode was adopted. Thirdly, the development of 1 000 MW-level nuclear power technology and economy model used for benchmarking and defining the principles and standards for cost control in the preliminary stage were discussed.Fourthly, the research and implementation of "integration of nuclear power and pumped-water storage" to ensure the competitiveness of on-grid price of nuclear power were discussed. Fifthly, the establishment of effective cost control mechanism for nuclear power projects and staff cost control culture were discussed. [Results] The above lean management methods and measures can directly save a large amount of investment for the Zhangzhou nuclear power project in the preliminary stage, shorten the construction period of the Zhangzhou nuclear power project, reduce the construction cost of the nuclear power project, and further increase the competiveness of the on-grid electricity price for the Zhangzhou nuclear power project. [Conclusion] The construction cost lean management in preliminary stage of Zhangzhou Nuclear Power Project is very effective, not only can improve subsequent competitiveness of on-grid electricity for Zhangzhou nuclear power project, but also reduce nuclear power construction cost and improve the economy of nuclear power .And the Zhangzhou nuclear power mode and experience can provide reference for the nuclear power industry.
-
References
[1]
|
黄政宇. “华龙一号”核电工程混凝土管理模式研究 [J]. 南方能源建设,2016, 3(3): 116-121.
HUANG Z Y. Research on concrete management patterns of HPR 1 000 NPP [J]. Southern Energy Construction, 2016, 3(3): 116-121. |
[2]
|
孙汉虹,程平东. 核电工程项目管理[M]. 北京:中国电力出版社,2006,11(1): 4-11.
SUN H H. CHENG P D. Nuclear Project Management [M]. Beijing: China Electric Power Press,2006,11(1):4-11. |
[3]
|
何润财,涂国富. EPC工程总承包项目中采购成本控制 [J]. 南方能源建设,2016, 3(增刊1): 173-176.
HE R C, TU G F. Procurement cost control in EPC general contract project [J]. Southern Energy Construction, 2016, 3(Supp.1): 173-176. |
[4]
|
汪映荣,中电投核电有限公司.核电前期工作指南 [M]. 北京:中国电力出版社,2012: 10-98.
WANG Y R, CPI Nuclear Power Co., Ltd. Nuclear Power Preliminary Work Guidance [M]. Beijing: China Electric Power Press, 2012: 10-98. |
[5]
|
刘小坚. 核电前期项目公众沟通问题研究 [J]. 南方能源建设,2017, 4(4): 8-14.
LIU X J. Research on public communication of nuclear preliminary project in China [J]. Southern Energy Construction, 2017, 4(4): 8-14. |
[6]
|
李永华,白晋华. 结合福岛核事故探讨IAEA核电厂设计安全要求 [J]. 南方能源建设,2015, 2(4): 155-158.
LI Y H, BAI J H. Study on the safety requirements of nuclear power plants design based on Fukushima nuclear accident feedback [J]. Southern Energy Construction, 2015, 2(4): 155-158. |
[7]
|
秦晋. 海外总承包项目前期税务筹划分析 [J]. 南方能源建设,2017, 4(增刊1): 179-184.
QIN J. Analysis of advance tax planning for overseas EPC project [J]. Southern Energy Construction, 2017, 4(Supp.1): 179-184. |
[8]
|
张羽,胡亮. 关于总承包业务设计优化、采购成本控制的思考 [J]. 南方能源建设,2016, 3(增刊1): 165-167+185.
ZHANG Y, HU L. Design optimization and procurement cost control of EPC project [J]. Southern Energy Construction, 2016, 3(Supp.1): 165-167+185. |
[9]
|
张菊梅,苏非,吴强,等. 浅析“十一五”及“十二五”期间抽水蓄能电站造价水平 [J]. 南方能源建设,2017,4(增刊1): 150-153.
ZHANG J M, SU F, WU Q, et al. Analysis of the cost level of pumped storage power station during the 11th five year plan and the 12th five year plan period [J]. Southern Energy Construction, 2017, 4(Supp.1): 150-153. |
[10]
|
罗莎莎,韩冰,刘云,等. 广东抽水蓄能电站功能发挥情况研究 [J]. 南方能源建设,2017, 4(3): 69-74.
LUO S S, HAN B, LIU Y, et al. Research on the main functions of pumped-storage plants in Guangdong [J]. Southern Energy Construction, 2017, 4(3): 69-74. |
-
-